Measured engineering evidence

Measured Hotel Electricity Case Studies

Explore anonymised examples of our electrical diagnostic investigations. Each report uses measured data and engineering analysis to identify where electricity is being used, why unnecessary consumption occurs and which actions offer a commercially worthwhile return.

Report A

Reducing Hotel Electricity Costs Through Better Control

A large hotel investigation identifying potential annual savings of £27,000–£32,000 through improvements to plant-room controls, kitchen ventilation and lighting.

View Full Report A
Report B

Independent Assessment of a Proposed Voltage Optimisation Installation

An engineering investigation examining whether a proposed capital investment was justified by the hotel’s measured electrical characteristics and operating profile.

View Full Report B

Both reports open in a new browser tab. Client and hotel identities have been removed.

Stop Wasting PowerHotel Case Study

Case Study

How a Large Hotel Could Reduce Electricity Costs by £27,000–£32,000 a Year

A measured electrical investigation identified substantial savings through better control of existing systems — without compromising guest comfort or replacing serviceable plant.

Indicative annual saving
£27,000–£32,000
Electricity cost reduction
15–20%
On-site investigation
72 hours

Challenge

Despite previous investment in energy-saving technology, including voltage optimisation, the hotel continued to carry a substantial electrical base load overnight.

The challenge was to establish which systems were responsible, why they continued operating during lower-demand periods, and where further investment would deliver a worthwhile commercial return.

Investigation

Temporary electrical monitoring was installed across the hotel’s main incoming supply and selected distribution boards. Demand was recorded at 30-second intervals during normal operation, with the main supply monitored for approximately 96 hours.

  • Plant-room pumps, Variable Speed Drives and BMS controls
  • Kitchen ventilation plant
  • Staff and public-area lighting
  • Guest-bedroom distribution
  • Voltage optimisation and power-factor performance

Measured profiles were compared across occupied and off-peak periods, supported by physical inspection of the relevant engineering systems.

Key Findings

Overall finding  The greatest opportunities related to the operation and control of existing engineering systems, not wholesale plant replacement.

Plant-room demand

The principal opportunity was in the plant room. Pumps appeared suitably sized and serviceable, but the measured profile indicated that the control strategy no longer reflected varying operational demand.

Monitoring chart showing the plant-room electrical demand profile across occupied and off-peak periods
Plant-room electrical demand profile from the source monitoring chart.
Measured observation  Demand reduced only modestly during off-peak periods despite lower hotel demand. Major plant appeared to operate largely independently of actual building requirements.
DateOff-peakPeak
Sat 27 May47.2 kW54.8 kW
Sun 28 May31.8 kW51.0 kW

Other findings

Kitchen ventilation. Approximately 70% of the monitored load remained overnight. Programmed control offered an estimated annual saving of £4,000–£7,000.

Staff-area lighting. Fluorescent lighting operated for prolonged periods irrespective of occupancy. LED replacement and occupancy controls offered an estimated saving of approximately £12,000 a year.

Public-area lighting. Existing LED lighting operated through daylight hours despite substantial natural light. Better daylight and time control could save an estimated £2,000–£5,000 annually.

Guest-bedroom block. Demand fell to approximately 0.1 kW off peak and responded correctly to operational demand. No intervention was recommended.

Power factor. Performance remained excellent at 0.98–0.99. No additional power-factor-correction expenditure was justified.

Recommendations

  • Recommission the plant-room pump and BMS control strategy.
  • Investigate the bypassed Variable Speed Drive and verify sensors and pump settings.
  • Introduce seven-day scheduling for kitchen ventilation.
  • Replace appropriate staff-area fluorescent fittings with LEDs and occupancy controls.
  • Add daylight and time control to public-area decorative lighting.
  • Retain the existing bedroom controls and power-factor correction.
  • Re-monitor affected systems after implementation to verify savings and performance.

Outcome

The investigation identified a conservative potential saving of £27,000–£32,000 per year, equivalent to an estimated 15–20% reduction in total electricity costs.

The strongest opportunity came from improving how existing plant was controlled. The priority plant-room improvements were expected to cost approximately £4,000–£5,000, with an indicative payback of three to five months.

By measuring individual systems before recommending investment, the hotel received a practical action plan focused on reducing operating costs, protecting guest comfort and avoiding unnecessary capital expenditure.

Engineering conclusion  The opportunity was one of control, not equipment replacement. Recommissioning the existing strategy offered the strongest commercial return while making full use of the client’s existing investment.

Plant-room electrical demand profile from the source monitoring chart.

Stop Wasting PowerHotel Case Study

Case Study 2

How Electrical Profiling Prevented Unnecessary Investment — and Revealed £11,000–£17,000 of Annual Waste

An independent investigation found that a proposed voltage optimisation system was unlikely to provide a worthwhile return. However, one unusual electrical profile revealed something far more important: approximately 7 kW being consumed continuously while delivering little or no useful cooling.

Continuous wasted demand
Approx. 7 kW
Estimated annual cost
£11,000–£17,000
Proposed capital investment
Not recommended

Challenge

A modern city-centre extended-stay hotel was considering installing a voltage optimisation system to reduce its electricity costs.

Before committing to the proposed investment, Stop Wasting Power was asked to determine whether the hotel’s measured electrical characteristics supported the installation—or whether better opportunities existed elsewhere within the building.

The challenge was not simply to decide whether voltage optimisation could work. It was to establish whether it represented a commercially worthwhile investment for this particular hotel.

Investigation

Temporary electrical monitoring equipment was installed on representative distribution boards serving:

  • The main plant room
  • Guest accommodation
  • The commercial kitchen
  • Reception and public areas
  • Air-conditioning systems

Electrical demand, current, voltage and power factor were recorded over several days. The resulting load profiles were assessed alongside a physical inspection of the hotel’s engineering systems and discussions with its maintenance team.

The investigation compared how each system behaved during occupied and quieter periods, looking particularly for fixed loads, abnormal operating patterns and electricity consumption that did not respond naturally to changing demand.

Key Findings

Overall finding  Measurement prevented an unsuitable capital investment while revealing a separate operational fault responsible for significant continuous electricity waste.

Most of the hotel was operating well

The plant room, guest accommodation, kitchen, reception and public-area distribution boards all behaved as expected.

Demand reduced during quieter periods and increased naturally as occupancy and operational activity resumed. Power factor was generally satisfactory, and no widespread uncontrolled electrical load was identified.

Voltage optimisation was not supported by the evidence

The hotel contained substantial numbers of modern electronically controlled loads, including Variable Speed Drives, inverter-driven equipment, switch-mode power supplies and LED lighting.

These systems are designed to maintain their required output across a range of supply voltages and therefore offer less opportunity for savings through voltage reduction alone.

The installation would also have required substantial modifications to the hotel’s existing electrical distribution infrastructure. In view of the measured evidence, the proposed investment could not be commercially justified.

One electrical profile was completely different

Unlike every other monitored system, the air-conditioning distribution board remained almost perfectly flat at approximately 7 kW—hour after hour, day after day.

Air-conditioning electrical load profile showing demand remaining close to 7 kW throughout the monitoring period
Air-conditioning distribution-board profile showing an almost constant load close to 7 kW.
Measured observation  A functioning air-conditioning system should respond to changing occupancy, temperature and cooling demand. This almost-flat profile required investigation.

The hotel’s maintenance team confirmed that an associated condenser had failed and was awaiting repair. Although the condenser had been isolated, the associated fan continued operating because the required cooling condition could never be achieved.

Electricity was therefore being consumed continuously while delivering little or no useful cooling.

The estimated cost of this unnecessary operation was approximately £11,000–£17,000 per year.

Recommendations

  • Do not proceed with the proposed voltage optimisation installation.
  • Isolate the fan or fans associated with the failed condenser to prevent further unnecessary consumption.
  • Repair or replace the failed condenser.
  • Recommission the affected air-conditioning system.
  • Repeat the electrical monitoring to confirm that demand once again varies in response to genuine cooling requirements.

Outcome

The investigation prevented the hotel from committing capital to a voltage optimisation system that was not supported by its measured electrical characteristics.

More importantly, it uncovered approximately 7 kW of continuous electricity consumption within an air-conditioning system that was delivering little or no useful cooling—an estimated annual cost of £11,000–£17,000.

The remaining monitored systems were shown to be responding appropriately, allowing the hotel to concentrate its attention and expenditure on the one area where engineering intervention was genuinely required.

Engineering conclusion  Measurement did more than test the proposed investment. By comparing the electrical behaviour of individual systems, it exposed a hidden operational fault that conventional billing information could never have explained.